Monadelphous KT 

Scope of Work:

The scope of works include the detailed design, procurement, construction, testing and handover of approximately 7km of the 42" onshore Gas Export Pipeline (GEP) and approximately 3 km of the 12" Fuel Gas Pipeline (FGP) and associated facilities.

Gas Export Pipeline

The main elements of the GEP part of the Works are:

  • Civil enabling works along Wickham Point Road
  • Civil enabling works along the LNG plant site access road
  • Wickham Point Road crossing
  • 42" Pipeline and associated works
  • Pig receiver and inlet facility works

Fuel Gas Pipeline

The main elements of the FGP part of the Works are:

  • Tie In Station to PWC gas supply pipelines
  • 12" Pipeline and associated works
  • Inlet facility works.

Monadelphous

Scope of Work - Utilities and Off site Areas:

The Scope of Work for this package comprises the supply of supervision, manpower, equipment, tools, consumables, etc, for the mechanical works, and includes the following:

  • Installation of stick-built steel structures including steel shelters
  • Installation, including rigging, hauling, assembling, setting, aligning, etc, of non-module mechanical equipment (vessels, columns, internals & externals, heat exchangers, packaged equipment, rotating machinery, flare equipment, transformers, refractory, etc)
  • Installation of piping, including the hook-up and tie-in of module piping systems, NDT and pressure testing
  • Assistance for heavy lifting work, such as preparing foundations, alignment, grouting, etc.

Indicative work volumes for the Scope of Work are:

  • Steelwork Erection: 2,500 Ton
  • Piping (Hook-Up): 30,000 Inch-Dia
  • Piping (Stick-Built): 110,000 Inch-Dia