AGC Meisei Joint Venture (AMJV)

Scope of Work:

The scope comprises the supply of paint and the painting of the interconnecting piping spools between modules and site assembled steel and equipment for the Bladin Point site. Also includes the application of all types of insulation materials on the external surfaces of field installed equipment, piping and instruments including interconnecting piping between modules.

Painting Works

The proposed facilities are to be a modular design; the modules will be fabricated and completed including painted, at overseas module fabrication yards. Therefore, the scope for the Bladin Point site comprises the supply of paint and the painting of the interconnecting piping spools between modules and site assembled steel and equipment.

The main scope for Site Painting is touch up and includes:

  • Surface Preparation
  • Finish Painting
  • Lettering and Marking

The Painting comprises three categories of activities:

1. Site Installed: this category comprises the painting of items that are “stick built” erected and installed at site:

  • Prefabricated pipe spools- application of primer coat, intermediate coat and final coat on joints and touch up after erection.
  • Field erected piping- touch up on field joints.
  • Steelwork- touch up of such items as platforms, stairs, and handrail.
  • Touch up painting of equipment.

2. Hook Up: this category comprises the surface preparation, application of primer coat(s) and application of intermediate and final paint coat(s) to pipe spool “pup” pieces for interconnecting pre-assembled modules and stick built modules.

3. Relevant to Modules: this category comprises the touch up painting to items within the module components including piping and steelwork.

The painting works will include all necessary repairs on primer coat, intermediate and finish coats with all necessary testing and inspections being complete at each stage.

SITE ENGINEERING AND QA/QC

Engineering & QA/QC services required to ensure the Works will be performed include:

  • Monitoring and supervision to ensure compliance with specifications.
  • Inspection, testing and witnessing of work execution.
  • Preparation and submission of all test and inspection records.

Insulation Works;

The Scope of Work for this package includes the application of all types of insulation materials on the external surfaces of field installed equipment, piping and instruments including interconnecting piping between modules.

The work includes:-

  • The application of hot insulation materials with protective jacketing to equipment such as drums and vessels, piping, valves and instruments. It also includes personnel protection,
  • The application of cold insulation materials with jacketing to equipment such as drums and vessels, piping, valves and instruments.
  • The application of acoustic insulation materials with jacketing to equipment such as drums and vessels, piping, valves and instruments.

The Scope of Work includes the supply of all the material to carry out the insulation works.

Estimated approximate insulation quantities for Stick Built and Hook Up are as follows:-

  • Hot Insulation: Equipment (5,700m2) + Piping (1,300 m) + Elbow (460pcs) + Valves/Flanges (10,700pcs) +Piping Hook (640 PNT)
  • Cold Insulation: Equipment (3,500m2) + Piping (2,700 m) + Elbow (940pcs)+Valves/Flanges (13,500pcs) + Piping Hook Up (860 PNT)
  • Acoustic Insulation: Equipment (180m2) + Piping (2,200 m) + Elbow (530pcs)+Valves/Flanges (4,400pcs) + Piping Hook Up (240 PNT)